← Back to CBAM Insights
CBAM Ukraine steel relief

Ukrainian Steel and CBAM: Plants Are Halting, Relief Is Still Not on the Table, and Your 2026 Obligation Stands

Ukrainian Steel and CBAM: Plants Are Halting, Relief Is Still Not on the Table, and Your 2026 Obligation Stands

For importers of Ukrainian steel, the problem is shifting from cost to supply. Several integrated plants have stopped production after missile strikes, producers are asking Brussels for temporary CBAM relief, and so far none has been granted.

What ArcelorMittal announced

On 25 September 2026, ArcelorMittal said it cannot safely and sustainably restart ArcelorMittal Kryvyi Rih after four missile strikes in five weeks, according to cbamguide.com's report. The most recent strike was on 21 September. The group reported that five workers were killed and 17 injured, is taking a non-cash impairment charge of about $1 billion, and has given no restart timeline. Pre-war capacity exceeded 7 million tonnes of crude steel a year, and output has run between 1.0 and 1.65 million tonnes annually since 2022.

The same report says Kametstal and Zaporizhstal have also halted, which would put three integrated plants out of production in September 2026. Figures for Kametstal and Zaporizhstal come from SteelOrbis and should be read as reported, not confirmed.

Where the CBAM relief requests stand

Ukrainian producers and industry associations have asked the Commission to invoke the temporary-relief provision of the CBAM Regulation for exceptional and unforeseeable circumstances. Metinvest renewed its request on 22 September, and Pascal Lamy suggested on 24 September that Ukraine's exemption could be made conditional on EU accession progress and climate-policy alignment, including a domestic ETS.

The institutional response so far:

  • December 2025: the Commission refused Ukraine force-majeure relief before the definitive CBAM regime began.
  • 15 September 2026: Parliament's negotiating mandate on the downstream extension contains no Ukraine carve-out.
  • Trilogues: relief could still enter the legal text through the negotiations on CBAM's scope extension, which continue on 30 November.

cbamguide.com notes that no formal, dated exemption request document has been made public, so the exact form of the current request cannot be independently confirmed.

star Important

Until a legal change is adopted, CBAM obligations on Ukrainian-origin goods apply as written. A request for relief, or a political statement in its favour, does not suspend certificate obligations.

What this means if you import Ukrainian steel

Certificate obligations on 2026 imports remain due despite the plant halts. The practical risks sit elsewhere:

1
Confirm your supplier's production status

Ask the mill directly whether the plant that produced your steel is operating, and which plant will produce your next order.

2
Protect your emissions data

If a mill is offline, check you hold the actual emissions data for steel already shipped. It may be harder to obtain later and the alternative is default values.

3
Cost the replacement before you switch

Switching to blast-furnace steel from Türkiye or Asia changes the embedded emissions in your declaration, not just the price per tonne.

4
Keep melt-and-pour evidence

Since 1 October 2026, importers of covered steel must evidence the country of melt and pour, which applies to any new supplier too.

The wider context

The steel sector contributed 7% of Ukraine's GDP last year, according to the Kyiv Independent as cited by cbamguide.com, and Russia has reportedly launched at least nine ballistic missile attacks on the industry since August 2026. Those figures explain why the political pressure is strong. They do not change the legal position for importers today.

FAQ

help_outlineIs Ukrainian steel exempt from CBAM?expand_more

No. No exemption has been adopted. The Commission refused force-majeure relief in December 2025, and Parliament's September 2026 mandate has no Ukraine carve-out.

help_outlineCould relief still be granted?expand_more

Possibly through the trilogue negotiations on the downstream extension, or through the Regulation's temporary-relief provision. Neither has produced a decision yet.

help_outlineDo I still owe certificates if the plant that made my steel has stopped?expand_more

Yes. The obligation relates to goods already imported. It does not depend on whether the producing plant is operating today.

help_outlineDoes this affect Ukrainian fertiliser or aluminium?expand_more

The reporting behind this post covers steel only. If you import other Ukrainian CBAM goods, check your own supplier situation separately.